Only 22 months after the hottest construction, Chi

2022-08-09
  • Detail

Only 22 months after the start of construction, China invested in the construction of Pakistan's largest thermal power station and put it into operation

Abstract: each node is realized ahead of schedule or on schedule, which fully demonstrates China's speed and strength. Pakistanis who have been to the project site 5 e/W2 M9 D! J3 C, F0 r members were all amazed that sahiwar power station is currently the fastest growing thermal power project in the China Pakistan Economic Corridor

on May 25, the most obvious trend in the future development of polyurethane industry in sahiwa, China Pakistan Economic Corridor, is industrialization. The full load operation ceremony of unit 1 of Al wahar coal fired power station was held in sahiwar City, Punjab province, eastern Pakistan, marking the first large-scale energy project within the framework of China Pakistan economic corridor was put into operation for power generation. More than 500 Chinese and Pakistani friends from all walks of life, including Pakistani Prime Minister Sharif and Chinese ambassador to Pakistan sun Weidong, attended the ceremony

after 168 hours of full load test run, unit 1 of sahiwar coal-fired power station was successfully put into operation for power generation a few days ago. It is reported that this is the first high-efficiency coal-fired power unit put into operation in the China Pakistan Economic Corridor. It is also the coal-fired power generation unit with the largest single unit capacity, the most advanced technology and the fastest construction speed in Pakistan

on May 24, unit 1 of Huaneng Pakistan sahiwar coal fired power station successfully passed the 168 hour full load test run, becoming the first efficient and clean coal-fired power generation unit put into operation in the China Pakistan Economic Corridor

the Sahiwal coal fired power project is jointly invested and constructed by China Huaneng Shandong Power Generation Co., Ltd. and China Shandong Ruyi group. It is a "priority implementation" project of the China Pakistan Economic Corridor and the first large-scale, efficient and clean coal-fired power project constructed overseas by Huaneng in response to the "the Belt and Road" initiative

the project was officially launched in March 2014 and officially started in July 2015. It is planned to build two 660 MW supercritical coal-fired generating units. Unit 2 of the power station is scheduled to be officially put into operation at the end of June this year. After the completion of the power station, the annual power generation is expected to reach 9billion kwh, which is expected to meet the electricity demand of 10million people in Pakistan, and is expected to fill a quarter of Pakistan's electricity gap

with the economic growth and improvement of living standards in Pakistan, Pakistan is facing serious power shortages. In 2015, the power gap was about 6.4 million KW, seriously restricting the development of social economy; The country is facing a serious power crisis, which has led to a slowdown of 3% to 4% in GDP growth each year. Most parts of the country are facing power cuts of more than 8 hours, which are more serious in rural areas, and the lives of ordinary people have been seriously affected

after the sahiwar project is put into commercial operation, it will significantly improve the stability and capacity of Pakistan's electricity, provide a good energy foundation for local economic development, and create good conditions for the start-up and development of some industries

Pakistani Prime Minister Sharif said at the ceremony on the same day that it took only 22 months for sahiwar unit 1 to start construction and power generation, which is unprecedented in the history of Pakistan. The project will help Pakistan overcome the energy shortage and benefit the Pakistani people. p>

Pakistani Prime Minister Sharif attended the full load operation ceremony of unit 1 of sahiwar coal fired power station in the China Pakistan Economic Corridor

sun Weidong said that as a major project of the "the Belt and Road", the important role of the China Pakistan Economic Corridor has been valued and appreciated by all parties. As long as we always adhere to peaceful cooperation, openness and inclusiveness, mutual learning, mutual benefit and win-win results, we will continue to promote the construction of the "the Belt and Road" and the China Pakistan Economic Corridor, and make greater contributions to regional development, prosperity and progress

Duan Changjie, deputy chief engineer and project manager of sahiwar coal-fired power station of Shandong electric power construction No.1 company under PowerChina, said in an interview with the people that coal-fired power stations adopt the world's leading supercritical technology, with high operating parameters and thermal efficiency, and add low-temperature economizers on the basis of traditional boilers to improve the utilization of heat energy. The unit 1 that has been put into operation can save 54000 tons of coal for Pakistan annually. In addition, the project is also equipped with electrostatic precipitators and desulfurization devices to ensure that all economic, technological and environmental indicators reach the international advanced level

Duan Changjie also said that the project construction has created more than 2000 local jobs and trained nearly 100 engineers for Pakistan

the sahiwar coal-fired power station project has been included in the list of "priority implementation" projects in the China Pakistan Economic Corridor, and enjoys a series of preferential policies on safety, taxation, financing, market competitiveness and further improving land and electricity charges determined by the cooperation agreement signed by the Chinese and Pakistani governments. The Pakistani government provides sovereign guarantees for the project

building power stations at a high temperature of 50 ℃

people who work together are "over life" friends

Punjab has a subtropical climate, with long summer, drought and little rain. This is a real "hot land". In May 2016, the construction site experienced extreme high temperature for two consecutive weeks. The highest temperature 2 was 49.7 degrees Celsius, which was achieved by strengthening supervision and random inspection

at the beginning of the project construction, due to the lack of on-site personnel, everyone has several positions. Engineering professionals should not only manage the project and plan, but also manage the materials and summary on site. Zhang Fuguo, the deputy general manager, arrived at the scene three times a day in the morning, noon and evening. The employee said that general manager Zhang was "long" at the scene; Chen Wei, the deputy chief engineer, postponed the date of returning home for three times in order to complete the major milestone goal of transferring plant power. He stayed at the construction site for more than half a year...

on July 31, 2015, the first concrete was poured, and the project officially started

on December 18, 2015, the main plant was hoisted

on April 14, 2016, the hoisting of the steel frame of No. 1 boiler was successfully completed

on November 22, 2016, the hydrostatic test of No. 1 boiler was successful

on December 20, 2016, the rotor of No. 1 generator was successfully installed once

on January 13, 2017, the cylinder buckle of 1 steam turbine was completed

on April 21, 2017, the pipe blowing of No. 1 boiler was completed

on May 7, 2017, the first meeting of the startup Acceptance Committee of No. 1 unit was held, and the whole unit was started

on May 25th, 2017, the power station achieved 665 days of safe production. During the trial operation of unit 1, the main technical indicators were excellent, and various environmental protection indicators such as dust removal and desulfurization were far better than Pakistan's national emission standards, achieving boiler water pressure, plant electrification, DCS power receiving, steam turbine capping, boiler pickling, ignition and pipe blowing, steam turbine impulse starting, and power generation 168 hour full load test run and other 9 "one-time success"...

unit 1 of sahiwar coal-fired power station was put into operation, and a huge 185 meter high chimney stood majestically

each node is realized ahead of time or on schedule, which fully demonstrates China's speed and strength. Pakistani personnel who have been to the project site are all amazed that sahiwar power station is currently the fastest growing thermal power project in the China Pakistan Economic Corridor. Pakistan praised it as unprecedented and created miracles, and named it "sahiwar speed"

chabaz, chief minister of Punjab province ˙ Sharif's visit to the China Pakistan Economic Corridor (CPEC) on May 7 will be completed in a transparent and rapid manner. With the help of CPEC, Pakistan is developing rapidly, and those who oppose CPEC are the enemies of the country. It is believed that under the leadership of prime minister Sharif, many energy projects can be completed as soon as possible to completely solve the problem of power shortage in Pakistan

on May 7, Wang Xu, general manager of Huaneng Shandong company, accompanied chabaz, chief minister of Punjab province ˙ Sharif inspected the central control room of sahiwar coal fired power station

it is reported that the No.2 unit of sahiwar power station will be put into operation in June this year. At that time, sahiwar power station will become the first green and environmental friendly coal-fired power station in Pakistan with the largest capacity and the most advanced technology. It is the first to start and put into operation in the China Pakistan Economic Corridor. The annual power generation of the power station is expected to exceed 9billion kwh, which can effectively alleviate the current situation of local power shortage, improve the management level of local thermal power industry, and promote the improvement of people's livelihood and economic and social development in Pakistan